To choose a Column Mounted Jib Crane that reaches every required work area safely, calculate the horizontal distance from the crane's rotation axis to the farthest required hook position. Do not assume the jib arm length is the same as the usable working radius. This guide explains the measurements, tools, capacity checks, and layout details to confirm before selecting a crane.

The working radius is the horizontal distance from the centerline of the column or rotation axis to the vertical line through the hoist hook. Measure to the hook position needed for the lift, not to the edge of the load or to the end of the jib arm. For a column mounted jib crane, the available radius is usually limited by the jib geometry, trolley travel, end stops, and the hoist's position on the trolley.
For purchasing, use the required hook positions and the manufacturer's stated working radius and trolley travel to confirm the model. Ask the supplier to clarify how the stated radius is measured.
Measure on the actual installation floor whenever possible. A drawing is useful for planning, but site dimensions can differ because of columns, guards, installed equipment, or changes made after the drawing was prepared.
Mark the center of the proposed crane column on the floor. This point is the reference for every radius measurement. If the crane has not been positioned yet, mark the proposed center using the installation drawing and verify that the column location is practical for anchoring, access, and operation.
List each point where the hook must pick up or place a load. Include the normal production points, loading and unloading positions, maintenance positions, and any planned future workstations. Mark the vertical hook centerline required at each point. Measure to the hook position that lets the load be attached or released safely, rather than simply measuring to the center of a machine or workbench.
Choose two perpendicular reference directions on the floor, such as the length and width of the work area. For each required hook point, record its horizontal offset from the column centerline in both directions. Label the offsets x and y. Keep all measurements in the same units and make sure they are horizontal plan-view measurements, not diagonal tape measurements taken at an angle.
For each pickup or set-down point, calculate the radius as follows: radius equals the square root of x squared plus y squared. For example, if a hook position is 3 meters in one direction and 4 meters in the other, the radius is 5 meters. Repeat the calculation for every marked point, because the farthest point may not be obvious from looking at the room.
Compare the calculated radii and identify the largest value. This is the minimum geometric radius the crane must cover for the listed tasks. Check the result against the actual site layout and the crane's trolley travel. A point may be within the calculated radius but still unreachable if the jib cannot rotate toward it or an obstruction blocks the hook path.
Ask the manufacturer or supplier for the hook's inner and outer travel limits, the effective working radius, and any fixed dead zones near the column or jib tip. Confirm that the hook can reach the marked positions without the trolley striking end stops and without the hoist or load contacting the column, wall, or jib structure. Do not select a crane based only on nominal arm length.
Review how the load will be attached, lifted, rotated, and lowered. Include the space needed for the load and lifting accessories to clear nearby equipment. Do not add an arbitrary radius allowance as a substitute for a layout check. If the workflow needs extra reach, show the additional hook position on the drawing and have the supplier verify it against the crane's geometry and capacity.
Record the column location, calculated radii, required hook positions, maximum lifted load, lifting accessories, rotation limits, and known obstructions. Provide this information to the crane supplier for confirmation. The final selection must meet the manufacturer's rated capacity and installation requirements, and the supporting structure and foundation must be reviewed for the forces generated by the crane.
Working radius and lifting capacity are separate selection checks. Determine the maximum total suspended weight, including the load and all equipment below the hook. Compare that value with the rated capacity of the proposed crane and hoist. Do not treat the crane's maximum capacity as available at every position unless the manufacturer confirms that rating for the configuration and duty.
Provide the supplier with the required radius, load weight, lifting frequency, rotation needs, and site details. Ask for written confirmation that the crane, hoist, trolley, mounting arrangement, and intended duty are suitable. For some jib crane designs, capacity depends on the configuration, support conditions, or operating duty. Use the manufacturer's documentation rather than estimating capacity from a general product description.
A column mounted jib crane transfers forces into its column, base, anchors, and supporting floor or foundation. Confirm that the proposed installation can support the specified crane and operating loads. A qualified engineer or the crane manufacturer should review the structure and anchorage where required. A radius calculation alone does not establish that the installation is safe.
Draw the crane column, jib sweep, trolley travel range, and each required hook position on the site plan. Mark walls, doors, machines, racks, lights, pipes, guards, and other potential obstructions. Confirm that the jib can rotate through the necessary angles and that the hook can approach each load from a workable direction.
The hook may reach a point while the suspended load still collides with an obstacle. Check the load's length, width, height, center of gravity, and movement path, along with the space occupied by slings or lifting attachments. Consider the clearance needed to attach the load, lift it clear, rotate the jib, and lower it at the destination.
Review the crane's mounting position, access for installation and maintenance, required rotation range, and any limits imposed by the building or work process. Identify whether personnel need to move through the area and whether the load's travel path crosses another operation. Resolve conflicts on the layout before ordering the crane.
The distance from the column axis to the jib tip can differ from the maximum hook radius because the trolley may not reach the tip. Confirm the manufacturer's effective hook travel and end-stop locations.
Radius is measured from the rotation axis, not from the outside surface of the column. Measuring from the column edge can create an error that affects every point on the layout.
List all required pickup and set-down positions. The farthest point may be an occasional loading, maintenance, or changeover location rather than the main workstation.
Working radius is a horizontal plan-view measurement. Do not include hook height, lift height, or a diagonal distance from the floor to the load when calculating it.
A hook position can be within reach while the load cannot safely pass through the space. Check the full movement path, load dimensions, sling arrangement, and rotation limits before confirming coverage.
Include lifting accessories in the suspended load and confirm the rating for the proposed crane configuration and duty with the manufacturer. Have the installation support and anchorage reviewed as required.
A concise specification helps the purchasing team compare suitable models rather than relying on an approximate arm length. Include:
Shandong Seven Sword Machinery Equipment Co., Ltd. can help purchasing teams review crane requirements and match a Column Mounted Jib Crane to the measured work area. Share a site layout, load details, and required hook positions with the supplier before finalizing the order. A careful radius calculation gives your team a clearer basis for choosing a crane that reaches the work safely and fits the actual process.
November. 09, 2026
Can an Existing Building Column Support a Jib Crane?November. 06, 2026
Are Jib Cranes Suitable for Warehouse Loading and Unloading?November. 05, 2026
How Often Should a Column Mounted Jib Crane Be Inspected?